PROJECTS UNDER GAP PHASE-II

NO. OF TOWNS UNDER THIS SCHEME -- 7 (SEVEN )
  • THE NAMES OF THE TOWNS-- !) HALISAHAR,GAYESPUR & KANCHRAPARA 2) NORTH BARRACKPORE 3) BARRACKPORE 4) KHARDAH 5) UTTARPARA-KOTRUNG 6) KONNAGAR 7) TOLLY’S NULLAH.
  • TOTAL NO OF APPROVED SCHEMES – 65 SCHEMES.
  • TOTAL APPROVED AA&ES VALUE UNDER GAP PH-II – 7666.51 LAKH.
  • UPTO DATE FUND RECEIVED FROM KMDA – 6467 LAKH
  • UPTODATE EXPENDITURE – 5948 LAKH.
  • THE NO OF SCHEMES ALREADY COMPLETED – 59 NOS.
  • THE NO OF SCHEMES YET TO BE COMPLETED – 6 NOS.
REASONS FOR NON COMPLETION OF 6 NOS SCHEMES:
  • LS –III ( N.BARRACKPORE) – LAND YET NOT RECEIVED FROM CANTONMENT BOARD.
  • I&D SEWER ( N. BARRACKPORE) – 90% COMPLETED, 10% SEWER LINE RELATED TO LS-III .
  • LS-1A ( BARRACKPORE ) – WORKS STOPPED DUE TO COURT ORDER.
  • STP-I ( BARRACKPORE)– TENDER CANCELLED DUE TO THE CHANGE IN TECHNOLOGY OF STP DESIGN IN THE RECENT SEWERAGE INTEGRATION DPR OF BARRACKPORE TOWN UNDER NGRBA.
  • LIFTING STATION UNDER GAYESPUR TOWN-CIVIL WORK COMPLETED ,ELECTROMECHANICAL WORKS HAS BEEN INCLUDED IN THE COMPREHENSIVE SEWERAGE DPR UNDER NGRBA AND ACCORDINGLY CONSIDERED IN THE TENDER DOCUMENT.
  • MPS UNDER GAYESPUR TOWN- CIVIL WORK COMPLETED , ELECTROMECHANICAL WORKS HAS BEEN INCLUDED IN THE COMPREHENSIVE SEWERAGE DPR UNDER NGRBA AND ACCORDINGLY CONSIDERED IN THE TENDER DOCUMENT.

NOTE: ALL THE ABOVE 4 WORKS HAVE BEEN INCLUDED IN THE COMPREHENSIVE SEWERAGE INTEGRATION PROJECT OF NORTH BARRACKPORE & BARRACKPORE TOWN UNDER NGRBA.